Viaduc de Millau

 

Multi-span cable stayed bridge, 2.5km long, 378m span. Bid Designer, responsible for the concrete deck proposal; design check, construction methods, external consultant manager, BOQ. External consultants: Leonhardt and Partners, Florencio del Pozo (PROES); Javier Manterola y Miguel Angel Astiz (Fernandez Casado ingenieros).

 

Role: Bid Structural Designer

 

Client: Cintra

 

Company: Ferrovial-Agroman

 

Millau, France. 2000

Bids

Viaduc de Millau

 

Multi-span cable stayed bridge,
2.5km long, 378m span. Bid Designer, responsible for the concrete deck proposal; design check, construction methods, external consultant manager, BOQ. External consultants: Leonhardt
and Partners, Florencio del Pozo
(PROES); Javier Manterola y Miguel Angel Astiz (Fernandez Casado ingenieros).

 

Role: Bid Structural Designer

 

Client: Cintra

 

Company: Ferrovial-Agroman

 

Millau, France. 2000